Before you set the Bill of Material and Item assembly you need to set item maintenance with categories:
Finished good
Raw Materials
Packaging Materials
Labour Costs
To set the Bill of Material:
Access the Bill of Materials:
Navigate to Inventory & Services and select Build from Bill of Materials.
Click on Add Materials to begin.
Add Finished Goods and Materials:
Search for the Finished Good Item you want to assemble.
Add the following components:
Raw Materials (e.g., No. 1 Raw Materials)
Packaging Costs
Labour Costs
Specify the required quantities for each component.
Create Multiple Sets:
You can group materials into Set/Built No. 1, which includes a list of raw materials, packaging, and labour costs.
If needed, create a separate group as Set/Built No. 2 with different raw materials, packaging, and labour costs.
Assign to Finished Goods:
Assign each set (No. 1 or No. 2) to the same Finished Good Item or apply them to different Finished Goods as required.
Steps for Item Assembly:
Access Item Assembly:
Navigate to Inventory & Services and select Build from Item Assembly.
Select Supplier:
In the Supplier No. field, use the arrow-down key to select ASSM/999.
Add Details:
Add the Finished Good item.
Specify the quantity.
Enter the BOM (Bill of Materials) Number.